skip to main content

City of Rifle: Streets Projects Open House - Feb 18, 2025
Updated 5 days ago

February 18th, 2025

Captions
  1. So I really appreciate

  2. All of you guys coming out.

  3. My name's Patrick Waller, be no moment over,

  4. but I'm the city manager

  5. For the city of Rifle and this is, this is Craig Spalding,

  6. he's the city engineer for the city

  7. and he's gonna talk to us about all sorts

  8. of street projects, our street impact fees, our fund,

  9. how it all sort of works from budgetary perspective as well

  10. as we've got plan into this year.

  11. So I end with Craig. Alright, go ahead. Thanks Craig.

  12. So thanks everybody for being here.

  13. I'm the engineer for the city.

  14. I oversee all the capital

  15. and maintenance projects, so that's streets

  16. and then usually all the water

  17. and sewer projects that are out

  18. underneath the streets wind up being mine as well.

  19. And then as we talk to some of the cemetery

  20. or just some of the other stuff that goes along with that.

  21. But tonight we're gonna be talking mostly about

  22. streets projects.

  23. We're gonna kind of go into depth on how we prioritize

  24. and decide which streets we're gonna be working on

  25. and then go into some conditions of what rifle streets are

  26. and then we'll look at some past projects

  27. and then some projects that we have coming up this year.

  28. So there, there's quite a bit of stuff.

  29. So I can speed up or slow down.

  30. Feel free to interrupt me or ask any questions as I'm going.

  31. I'll try to keep it somewhat entertaining for you guys.

  32. So this here, this is the pavement curve.

  33. So basically all of the maintenance on pavements kind

  34. of decided on this.

  35. This is as asphalt gets older

  36. and then this is actually its score.

  37. So a road that's got a zero is failed.

  38. A road that's a hundred is brand new.

  39. You can see the curve's pretty flat

  40. for almost half of its life.

  41. So if you, you build a new road,

  42. it doesn't really start getting bad until the,

  43. after about seven to 10 years.

  44. And then after that it starts falling off really fast.

  45. So what you try to do is when they're in that part

  46. of their life, you do crack seals where you go

  47. through in any of the cracks in the road, you fill 'em with

  48. a joint sealant and then you put, we do HA five,

  49. which is a coating that you can put down on top of 'em

  50. and it keeps the water out.

  51. But basically you're doing anything you can to keep water

  52. and sun from making the road older.

  53. And every time you do that, you can get it close

  54. to being a new road.

  55. It never gets all the way up to a new road,

  56. but you can kind of keep doing those crack seals

  57. and those surface treatments.

  58. And every time you do it kind of bumps it up

  59. and then it ages again, bumps it up.

  60. And eventually we have some roads

  61. and rifles that we can get instead of an average

  62. of a 20 year span, which is an untreated road,

  63. we've got roads that can get 30 to even 40 years

  64. before they have to get replaced,

  65. which is a big thing financially

  66. because everything's cost per square

  67. and then it's cost per year.

  68. So instead of having

  69. to replace all the roads every 20 years,

  70. if we can replace 'em every 40, then

  71. that cost per year goes down half.

  72. The other thing to note is that the,

  73. so for the cost of just a crack seal,

  74. which is something

  75. that you should be doing every five years, so this will be

  76. where we kind of look at the, the budget to the,

  77. but basically it's, it's 60 cents a square yard is

  78. what it costs us on average to do crack seals.

  79. Whereas if you look all the way down at replacements,

  80. they're $77 a square yard, so they're more than 10 fold

  81. more cost and you only get four times

  82. as much life.

  83. So definitely putting a priority on the crack seals

  84. and the surface treatments is what we bank on keeping, it's

  85. what keeps our good roads good.

  86. So we keep our good roads good while we try to fix all

  87. of the ones that are failing.

  88. Basically the way we've split it out in rifle is

  89. a crack seal lasts anywhere from five to seven years.

  90. So basically you're gonna be on average,

  91. sometimes you get more, sometimes you get less,

  92. but on average you're going back to every road.

  93. So every five years.

  94. So basically we take the entire cost of,

  95. if we were to crack seal all a rifle, split that in five

  96. and that's around $60,000 a year

  97. that we put into crack sealing.

  98. And then we do the same thing for surface treatments.

  99. So surface treatments, they last 10 to 15 years.

  100. So we take, if we were to do 'em every 10 years,

  101. so about 125

  102. and some of these, so I'll get into the projects

  103. that we're doing this year, but some of 'em

  104. wind up getting grouped.

  105. So like this year we have a big chip seal project

  106. that we're gonna do this spring.

  107. And it's three big roads.

  108. It's airport road 16th and seventh.

  109. So we didn't do a chip seal last year,

  110. but the one that we're doing this year, it's

  111. I think three 70 to 400,000 is the number on that.

  112. So, so once in a while a project might kind

  113. of take up two years, so you'll still get the same,

  114. but these are the averages that we have to make sure

  115. we're hitting on our maintenance

  116. or else it might feel like we're doing lots,

  117. but then all of these good roads will catch up

  118. to us in 15 years and we won't be where we want to be.

  119. And then replacement, so if you do your job on the,

  120. the crack seals and the surface treatments

  121. basically 35 years on just the replacement.

  122. Something to note with these numbers here is

  123. that's just the street.

  124. So a lot of times the,

  125. so these are, these are maintenance.

  126. So it seems like if you're doing a full replacement,

  127. it might be more of a capital project.

  128. But usually when we go to do a replacement, you wind up

  129. with a water line that's just as old as the road

  130. and then the curb and gutter and the sidewalk.

  131. So that $77 a square yard often winds up

  132. coming up quite a bit.

  133. But we kinda wind up with different funds we wind up with,

  134. there's the water fund that pays

  135. for the water sewer for the sewer.

  136. We wind up getting a bunch of grants to help pay for any

  137. of the sidewalk improvements and all the other things.

  138. So basically if we were to do just the road

  139. and neglect the everything on the sides

  140. and everything below for just maintenance alone, it,

  141. it's about 1.8 a year, 1.8 million just

  142. to, to keep up.

  143. And you can see, so everything in the, the yellow to red

  144. shades are, those are all surface treatments.

  145. So you can see about half of the roads at any given time

  146. and you'll just see these, this, this is a software

  147. that we have that we track.

  148. So every year we go out and we look at every street

  149. and we rate it based on how many cracks it has,

  150. are they going with the road

  151. or against the road, how thick they are,

  152. all the different things.

  153. And then that comes in to give us an overall rating

  154. and a remaining service life of the road.

  155. So this, and then you take that

  156. and then you can kind of determine if it's a really old

  157. road, it's ready for replacement.

  158. If it's new then it needs a chip seal

  159. or a crack seal or an HA five.

  160. But the, the crack seal

  161. you'll see happening pretty much all over rifle every year.

  162. And I kind of compare it

  163. to you just kinda run it independent.

  164. So I compare it to kind of like washing your vehicle.

  165. So sometimes you might be go camping the next weekend

  166. so you're like, well should I wash it?

  167. But it's always gonna make your vehicle last longer if

  168. you're doing those crack seals.

  169. So crack seal kind of runs independent of all

  170. of the other projects, whereas the other projects they wind

  171. up having to take in quite a bit of the other stuff.

  172. So one of the bigger other stuffs is waterlines.

  173. So, so rifle has 76 miles of waterline.

  174. This is a map of our waterlines with its rate

  175. and it's color coded by its priority of replacement.

  176. But essentially waterlines, if they were

  177. to last a hundred years, we would have

  178. to replace 1% every year.

  179. And that's, if they last a hundred years,

  180. they usually don't last that long.

  181. But even at, if they were to last a hundred years,

  182. we'd be replacing 1% every year.

  183. So for rifles 76 miles, that winds up being three quarters

  184. of a mile of which

  185. is 11 350 foot blocks per year.

  186. We would need to be replacing of waterline.

  187. So most of these blue roads,

  188. those are our replacement roads.

  189. Basically the, the priorities of the replacement roads

  190. wind up getting prioritized almost as much

  191. by the road as they do the water

  192. and the sewer for the most part other than,

  193. so in the last, in the last three to five years, most

  194. of our bad roads were also our main roads.

  195. So Railroad Avenue work on White River.

  196. So it was really easy to prioritize those

  197. because they're roads that impact everybody.

  198. But as we start getting further off of those roads, most

  199. of the priorities will, there's gonna wind up being lots

  200. of balancing between the basically the water and the sewer.

  201. And then there's gonna be times

  202. where the most important sewer line isn't

  203. underneath the most important road,

  204. which is different than the most important water,

  205. which is once we get into some of this year's projects,

  206. you'll see we have, we have some water and sewer

  207. and road projects kind of all over

  208. because we have different priorities for each one of them,

  209. all of which are super important for us to address.

  210. So I've got some pictures that I was gonna go over for some

  211. of the kind of like the last five years projects, but

  212. before I do so that that'll kinda lead us into

  213. what our existing conditions are.

  214. But before I do that, does anybody have any questions

  215. or anything they wanna address on just

  216. how we prioritize and rank our streets?

  217. Okay, so I'll kind of go through these somewhat quickly.

  218. Some of 'em, it's just kind of good to see

  219. what the streets of the kind of before

  220. and afters, you kind of forget how bad some of them were.

  221. So basically this is looking

  222. almost right outta city hall.

  223. So only six years ago

  224. there weren't any of the improvements to Centennial Parkway

  225. and basically the, the sidewalks were out of compliance,

  226. the streetlight needed repaired.

  227. So 2019 we were able to take basically the corner of town

  228. and by making all of those improvements,

  229. which was also water improvements

  230. and sewer, make it to what it is now

  231. and then just some quicker ones, swallow Lane,

  232. that's second Street.

  233. This is a good one to mention

  234. because we actually worked with Rocky Mountain Natural Soda.

  235. So this is kind of right out in front of their,

  236. their complex there.

  237. And they actually did a big cost share.

  238. So the road was getting pretty tore up by their,

  239. their large trucks and they were really great to work with.

  240. And basically we needed to replace the road with just,

  241. it would be normally just asphalt, but

  242. because of the size of their trucks, they are willing

  243. to work with us and then gave us a,

  244. did a cost share on the project

  245. and did this big concrete apron

  246. that lets those trucks pull out

  247. and turn out without causing damage.

  248. So you can kind of see the before and after.

  249. And it just kind of shows some of the community partners

  250. that we wind up with on some of these fravor and fifth.

  251. So only about five years ago there was

  252. basically going up the hill, the sidewalk, it went up

  253. and then just ended at a retaining wall

  254. and it was also at the blind part of the hill.

  255. So if you were walking up, you would get to this dead end

  256. and then you'd have to run across

  257. and hope no cars were coming over.

  258. So we were able to basically replace all this failed asphalt

  259. and we also replaced the waterline, which

  260. was originally installed in like the fifties.

  261. So Waterline got replaced, road got replaced,

  262. but then this was another one,

  263. an example of where we get grants.

  264. So this one got a big grant from the car,

  265. Garfield County Federal Mineral East District.

  266. So basically any of the money that the,

  267. that mineral leases on federal lands in our area,

  268. it winds up kind of going back to the state

  269. and then to the county and then the county distributes it

  270. via grants and they wind up funding quite a few

  271. of our projects, especially some of these big road projects.

  272. So we're able to not only fix the failed asphalt,

  273. but also make the road a lot safer and replace the water.

  274. And I think on this one we also did some

  275. of the sewer manhole.

  276. So this was kind of the, the full swath

  277. we try to, at least every other year do we just call it an

  278. asphalt patching and overlay project.

  279. So 2019 you wind up, you find spots.

  280. So this is actually right at the crest

  281. of the hill, a fire thorn.

  282. So at the top you can see just how failed the road was there

  283. and we just put out a contract and we go out

  284. and fix patches sort of all over.

  285. Sometimes it's an entire road

  286. or like in this case it was just about a hundred feet

  287. of road that gets replaced.

  288. But they're really, they're kind of quick projects

  289. with a big return on basically the before and after

  290. and what we're getting out of the project.

  291. This one shows Fire Thorn 2019.

  292. Another thing that streets covers is bridges.

  293. And so we have addressed basically all of our bridges

  294. at least in the last five years.

  295. So this shows the 16th Street bridge, which is the bridge

  296. by the skate park going across Rifle Creek.

  297. You can see before it had a lot of,

  298. so it was getting a lot of water through the, the sidewalk

  299. and then that was getting on all the girders

  300. and causing rust and structural damage.

  301. So we were able to chip all the concrete out

  302. and then put down a special coating

  303. and a paint basically to so sandblast to get rid of the rust

  304. and then put down paint to keep it from rusting anymore.

  305. And then you can see a new deck, new sidewalk,

  306. basically just to make sure that these bridges stay.

  307. So if if you address this, then

  308. you can keep it from turning into a,

  309. a major structural issue,

  310. the the Railroad Avenue bridge.

  311. So we went through and waterproofed it

  312. and resurfaced it just a couple years ago, you can see just

  313. how pitted and failed the surface was before we began.

  314. And then we stripped all the asphalt off

  315. and then stripped off the old waterproofing

  316. and then re waterproofed it

  317. and then put down the new asphalt.

  318. And probably, I think it was one of the bigger costs

  319. and you don't see it, but it was actually the

  320. waterproofing that we put down.

  321. So the most important part, so basically bridges fail due

  322. to rust and corrosion and grit.

  323. So if you can keep all that water on the surface

  324. and coming off the edges, you can make bridges

  325. and especially in Colorado in the drier climate last

  326. for, for very long times.

  327. So that waterproofing definitely extended that bridge

  328. and probably had more of a benefit than

  329. the surface that you can see.

  330. But the surface is still pretty nice to drive on

  331. the centennial bridge.

  332. So the,

  333. this is the bridge going across Rifle Creek on highway six.

  334. So Highway six is what we call it's Centennial Parkway.

  335. So it was devolved, which is a process where

  336. CDOT gives the right of way to the city.

  337. So from the bypass

  338. and one mile to the east is the city, so

  339. that's Centennial Parkway.

  340. So basically that was 10,

  341. 15 years somewhere in there

  342. where the city went through that process.

  343. And then by going through that process, they're able,

  344. the city we're able to do projects

  345. or add signs or do things on that stretch of roadway

  346. where if it was still cdot we'd have to go

  347. through all the CDOT processes and the purview.

  348. So it gives us a little bit more flexibility on

  349. how we develop and maintain those roads.

  350. So that bridge was actually ours

  351. and we took the entire deck off, as you can see here.

  352. So went and shipped all the concrete off

  353. and then did an inspection of the girders

  354. and found, so anywhere that the girders were pitted

  355. or rusted, we actually cut out new sections

  356. and then welded new sections in

  357. and then X-ray inspected those.

  358. So essentially when we were done, every one

  359. of the steel girders was like brand new

  360. and then it wound up getting a brand new deck.

  361. So, and,

  362. and that project, the cool thing about that is we were able

  363. to essentially we wound up with a brand new bridge,

  364. or at least the lifetime of a brand new bridge.

  365. And we did it for just short of a million dollars, which

  366. is is actually pretty usually when they're,

  367. people are talking about bridges,

  368. they're talking tens of millions.

  369. So for us to get it at that price was, was a huge success.

  370. So did you do the

  371. flood routing under on right underneath?

  372. Underneath that bridge?

  373. Yep. Yeah. So originally it was,

  374. and that's part of what caused some of the, so

  375. that abutment in the middle, the

  376. creek had actually kind of shifted to

  377. where it was just pointing right at it

  378. and it was kind of creating some scour in front of it.

  379. So what we did is we put a bunch of rip wrap

  380. or angular rock to make the creek stay in between

  381. these two abutments.

  382. So this is where the creek stays during normal time.

  383. And then ideally, so the way it was designed

  384. is when we get a regular high water,

  385. it'll actually flush out all of the silt.

  386. So they, they get the angle of all of that to where it,

  387. it'll silt up during low flows

  388. and then in the spring it'll flush that out

  389. and then if it gets higher than that,

  390. it can basically overtop that

  391. and then run in between these abutments.

  392. But we were able to, to improve

  393. not only the low flow but kind of the flood characteristics

  394. of the bridge

  395. Downtown.

  396. So these are some pictures before it kind of hard to imagine

  397. or remember back some of those, this, this was a,

  398. a crosswalk right at third where you can see the,

  399. the light came right out of the middle of the a DA ramp,

  400. which is not really compliant.

  401. You can't really get through there.

  402. And then you can also just see how SPD and the concrete was

  403. and how everything was coming apart.

  404. And then this is the, just a screenshot of in the summer,

  405. what this, that ramp here.

  406. So that picture, there was that same ramp there

  407. that's now fully compliant.

  408. So this project, the railroad project replaced all of the,

  409. the water lines downtown

  410. and it did it, so we replaced it with a 12 inch line,

  411. which is big enough if any

  412. of these buildings wind up needing fire suppression,

  413. it can supply enough flow.

  414. So it, it took the old line and then up-sized it.

  415. So not only replacing the old infrastructure

  416. but to putting a new, and then we also went

  417. and replaced all of the, the services as well.

  418. So there was some of the, some of the buildings,

  419. the services, especially on this side, the,

  420. so it'd be east third, they had just like crawl spaces

  421. and then there was only about this much

  422. and they made enough to

  423. where the skinniest guy on the job site could go through

  424. that little trench from one end of the building all the way

  425. to the other and then replace the service.

  426. So there was a lot of, lot of blood, sweat and tears

  427. and just getting some of those replaced that, that one,

  428. the guy he could go through and then fall through

  429. and then he could stand back up and replace it.

  430. But the only guy that was small enough

  431. to do it was actually a, a concrete worker.

  432. So then he had to put on his phone

  433. and have everybody tell him he wasn't a, a water guy,

  434. but he was the only one small enough to fit in the hole.

  435. This, this project had a lot of surprises for you, didn't

  436. It?

  437. It did, yeah. So there was, so there was, we

  438. expected surprises, but there was some that we didn't even,

  439. like in front of the Midland building,

  440. there was actually an old, the sidewalk was just on plywood

  441. and then there was a big staircase that went into the,

  442. so we were chipping out the concrete

  443. and then there's a piece of plywood and we picked it up

  444. and it's just a big cavern

  445. and concrete stairs going into the, the basement.

  446. And then almost every building had old coal shoots.

  447. So you would chip out the sidewalk

  448. and then it would just be a,

  449. and they just poured right over the top so there'd all

  450. of a sudden be a big hole into the side of a building.

  451. So we'd had a lot of those foundations we'd have to go

  452. through and patch with concrete and patch it

  453. and then re backfill and waterproof those.

  454. So lots of, lots of nostalgia there.

  455. We wound up, we found, so on the corner of,

  456. so it'd be in front of the Midland building,

  457. there was an old storm inlet

  458. and when we went to tear it out,

  459. it had a bunch of silver dollars.

  460. Oh cool. We were like, well that was pretty cool.

  461. So we took them and then I wound up, I found the story that,

  462. so it was actually an, an old, old relative,

  463. but they worked when, where Witten CO is now was the bank,

  464. they would walk out and they would flip their silver dollar

  465. and whoever got closest to the curb had to buy coffee,

  466. but if they messed up, their silver dollar would go down.

  467. So we found out that those silver dollars were most likely

  468. theirs from their, yep.

  469. Yeah.

  470. Oh,

    The bank, the bank was on this side,

  471. the left side was production credit association.

  472. I think you gotta go further

  473. This I

    Get, yeah.

  474. Is that production credit there?

  475. That was the production credit association

  476. And then the other side was a bank

  477. Way back.

  478. Okay. Yeah.

  479. So it was, it was, did you know Jim Lane was the one

  480. that would flip the PC?

  481. Yep, yep,

  482. So now I, I have a shelf in my office now

  483. of all these little tidbits.

  484. So I got little pieces of the old bridges

  485. and every time we do a project, try to put

  486. something on there.

  487. So one thing we didn't really go into when we completed it,

  488. but the, the downtown project actually wound up getting two

  489. national awards, one from the American Concrete Association

  490. and then one from the American Concrete

  491. Pavement Association.

  492. So as far as the, the installation

  493. and all of the, the final product, it wound up being a,

  494. a pretty heavily awarded project, which was, was kind

  495. of cool Once, yeah, yeah,

  496. 2022 asphalt improvements.

  497. So this is right in front of Moki Park.

  498. This seventh Street had been failed

  499. for quite some time.

  500. This is another one of those projects where we just jump

  501. around and fix fix chunks.

  502. So this is just kind of like the, the best before and

  503. after of the 2022 Asphalt paving

  504. and overlay Second Street.

  505. So Second Street's actually wound up getting a couple

  506. of grants, which is why we were able to do so much of it.

  507. Both of those grants came from cdot.

  508. So the first one, the first phase

  509. of it just did this sidewalk.

  510. So they gave us 50 grand

  511. and I think the sidewalk costs 70 grand.

  512. So we contributed 20 of our own

  513. and then they increased their grant to 250.

  514. So we were able to go back again

  515. and get the rest of the street.

  516. But you can look here, so this is on the north side

  517. of second Street, so only a few years

  518. ago you can see the sidewalk.

  519. That's, that's what the sidewalk was.

  520. And then on the south side there wasn't any sidewalk at all.

  521. So we were able to replace the sidewalk and the street.

  522. And then this one we were also, we had

  523. some storm drain issues that we were able to replace.

  524. So we did put new storm drain all the way up Second Street

  525. and then this lot here is lower than everything else.

  526. So we were able to stub that storm in to this lot

  527. and then stub a water service in there.

  528. So as we're doing projects, if there's the ability to try

  529. to get something in the ground so

  530. that the next person doesn't have to do it, we always try

  531. to take, take that opportunity,

  532. The signal.

  533. So this, this picture here,

  534. this is actually from the Google Street car.

  535. So if you actually go on Google Earth

  536. and you drop in, that's actually the image.

  537. So when the Google car went by with their camera,

  538. there was actually somebody just

  539. on their phone walking through the middle.

  540. So that was kind of the before and then the

  541. after of that project, which to date

  542. as far as vehicle crashes has been super successful in,

  543. I, I'll probably get the data wrong,

  544. but there was in, from the time it finished

  545. to earlier last fall, we ran an audit of

  546. how many crashes there were.

  547. And at time, that time there were no crashes.

  548. And in the same amount of time

  549. before the project there were 10.

  550. So there's a lot less crashes happening there.

  551. And we have given pedestrians something better

  552. to cross than right through the middle of the island.

  553. So fifth and railroad.

  554. So that was another intersection project

  555. where we got CDOT funding.

  556. So they funded just the a DA improvements, which we started

  557. the fall two years ago and then worked through the winter.

  558. So you can see this is the sidewalk here.

  559. You can tell it's far from a DA accessible, you couldn't,

  560. you could, you almost had

  561. to turn sideways just to walk through it.

  562. And then this is that same corner now the,

  563. this corner, there actually wasn't even a curb drop off,

  564. it was just vertical curb.

  565. So you'd have to step down off of it

  566. and then now it's got, got the ramp.

  567. And then once we finished that, we did the,

  568. the railroad fifth to ninth.

  569. That one was a, so it was the

  570. highest priority street project

  571. and one of the highest water.

  572. So it was primarily a water project we've had,

  573. we wound up having quite a few breaks in the water line at

  574. the intersection of fifth.

  575. So it was an old ductile line.

  576. And then the line that we were replacing had a line

  577. that ran from there and then through alleys

  578. and it was an eight inch line, went through a bunch

  579. of alleys and then all the way up to ninth

  580. and White River kind of in front

  581. of the district office for the school.

  582. And we couldn't, so anytime you had a break

  583. or you had to do maintenance, the only way to shut off

  584. that spot was to shut all the way from,

  585. from ninth to fourth.

  586. So you had to shut off almost the entire downtown

  587. just to do any work there.

  588. So we were able to abandon that old line

  589. by kinda systematically shutting things off.

  590. And then in one day we had to do four swap overs.

  591. So we had to basically get everything exposed the day before

  592. and then turn everything off that morning

  593. and then have multiple crews working in different spots

  594. to try to get the line all shut off, drained off

  595. and then capped, put back together

  596. and get people back in service at least by at evening.

  597. So this was a huge street project as well.

  598. You can kind of see how failed Railroad Avenue was

  599. before we started, but probably,

  600. I don't know, debatable the, the water improvements were,

  601. were pretty big as well.

  602. And we also, on railroad, we were able to line

  603. the sewer line from eighth Street to ninth Street.

  604. So there you, you take a, the, the sewer line was old

  605. material but still had good grade.

  606. So we were able to run basically

  607. a heated up plastic pipe in the middle of it

  608. and then you inflate it and then let it cool.

  609. So then it puts, you wind up with basically a superior

  610. 'cause it, there's no joint from that manhole all the way

  611. to the next, so no leaks in or out

  612. and you can do it for a lot less

  613. impact and a lot less money.

  614. So it's, it's kind of the, the lining is basically a,

  615. a better product for less money.

  616. So we got to, on this one, we got

  617. to fix basically everything, the water, the sewer,

  618. the sidewalks added lighting.

  619. We wound up having to do a lot of night work.

  620. Basically it wasn't,

  621. it was night work started in the morning

  622. and then just worked some of those.

  623. Water shutoffs were I think some of the,

  624. like the sewer switch over wound up being 16 or 18 hours.

  625. But when we were working in there in the dark,

  626. you could see from basically if you get off the highway

  627. to fifth Street, there's street lights all the

  628. way and then they stopped.

  629. They didn't pick up again until the fairgrounds

  630. and you didn't realize how dark that street was

  631. until you're working in the night.

  632. And so huge improvement to get those lights as well.

  633. So basically kind of with all of those projects,

  634. this is the basically the ratings that we have

  635. for our streets now

  636. where red is everything that needs.

  637. So it's all, this is all by remaining service life.

  638. So everything

  639. and we put all of this into a software so it winds up kind

  640. of lumping things together.

  641. But you can see most of our streets right now

  642. are in that we have a big chunk in the four to six range.

  643. I think we did. And it was with the state.

  644. We did an audit of our, our streets

  645. and then a lot of the other agencies that

  646. did the audit with us

  647. and our streets basically rated it a 61,

  648. which if you are thinking of going to school

  649. and a a 60 would be a D is not the greatest,

  650. but 61 for streets is actually about

  651. as good as you can do.

  652. So a hundred is basically perfect.

  653. So if you have, and then the,

  654. they call it the complaint line, but basically a 40

  655. and below is where you're starting to see lots of potholes.

  656. So basically the best you can ever really be is somewhere in

  657. the middle between 40 and a hundred.

  658. So you're always gonna, you wanna replace 'em

  659. before they get below 40,

  660. but you're always gonna be, the average

  661. of all your streets is gonna wind up should be,

  662. in a perfect world you would have an even distribution so

  663. that you're, you're just on a cycle.

  664. So in a perfect world you'd be basically right in between

  665. that 40 and a hundred.

  666. So 60 is actually a, a decent spot to be.

  667. And I guess before I was gonna take this

  668. and then talk about some of our projects

  669. that we have this year, but

  670. before I do, does anybody have any questions on this

  671. or the ratings or anything else we've gone over?

  672. No, that's it. Oh, thank you.

  673. So I was just gonna kind of take this map

  674. and then you can see these red streets,

  675. the first couple slides.

  676. So, so this is,

  677. these are all projects we're gonna do this year

  678. and these lines don't come in super great.

  679. So I can just kind of point 'em out. This is everything.

  680. We're in a crack seal this year

  681. and you can kind of see it's just scattered

  682. kind of throughout.

  683. These are, so basically a lot

  684. of these smaller streets in South Rifle

  685. Park Avenue and then a lot

  686. of these like Highlands East and then North Rifle.

  687. So most of these are all neighborhood streets

  688. and the crack seal, when we go

  689. and do it, it's usually, so it's a pretty quick operation

  690. but it's usually, it doesn't affect traffic as much.

  691. But if it's in a residential area

  692. and people are home all day,

  693. it does wind up being kind of loud.

  694. So they go through with a giant compressor

  695. and then blow all the dirt out of the cracks

  696. before they put 'em in.

  697. So they have to clean it. So that's the kind

  698. of the common complaint is

  699. that if people are staying at home, they have to listen to

  700. that compressor run all day.

  701. And then sometimes the, in cleaning the streets, some of

  702. that gets on the sidewalk, they, they always have

  703. to come back at the end and clean it off,

  704. but sometimes there's just so much dirt they can't,

  705. it's gotta go somewhere

  706. and it can't go on the road that they're trying to clean.

  707. So it winds up getting pushed to the edge

  708. and then they do other crack seal

  709. and then they come through with leaf blowers

  710. and push it back into the middle.

  711. But this'll be, we're shooting for April.

  712. I think the, the bids

  713. for this project actually come in this week

  714. and then it'll go to council for award.

  715. But kind of, it'll just be like, most of these

  716. are on the order of magnitude of hours on, on a street.

  717. So it's kind of a rolling operation, lower impact,

  718. but a little noisy, a little dirty.

  719. So all the red is under one contract?

  720. Contract? Yep. Requested

    Just

  721. One bid on?

  722. Yep. Wow. So sometimes, so we're actually,

  723. this will be like our last catch

  724. up year on the crack ceiling.

  725. So we kind of got behind a little bit on it

  726. and about five years ago we've been putting a big emphasis

  727. on getting caught back up.

  728. So in the past they've been like really targeted in a spot.

  729. So like five years ago everything was a north rifle

  730. and then we kind of picked neighborhoods,

  731. whereas this is gonna be sort of like the everything else

  732. to get us to where we should be.

  733. So at the end of this crack ceiling project,

  734. we'll be actually pretty nice and caught up

  735. and we might, we are actually starting to see some

  736. of the cracks from the first project six years ago now.

  737. We'll probably start having

  738. to do some more maintenance on those.

  739. So, but that's kind of where you wanna be is just

  740. that, that rotation.

  741. And then this is our chip seal.

  742. So it's airport road basically

  743. where the concrete ends at the roundabout to

  744. where the new asphalt starts, which is

  745. basically right at the last driveway of Walmart

  746. and the chip seal on airport road

  747. because there's so many lanes they're gonna be able to do,

  748. it's gonna be sort of a rolling detour.

  749. So they're always gonna be in one lane,

  750. but we don't expect closures

  751. and we expect the impacts to be

  752. minimized by the fact that there's four lanes

  753. and we'll be able to keep people in one

  754. of those lanes at any given time.

  755. When they go and actually do the chip seal, it'll be,

  756. I don't know that they'll do airport road seventh

  757. and 16th all in one day,

  758. but it's pretty amazing how fast they wind up.

  759. So they put all the oil down

  760. and then they have a piece of equipment

  761. that just pulls the trucks through

  762. and they just basically as fast as they can drive,

  763. they're putting the chip down on the new oil.

  764. And then

  765. Is that a double pan or just

    More?

  766. It'll be two. So we've got, well

  767. I think both of these are just a one,

  768. so just a three eights.

  769. So a and then we'll do a fog coat.

  770. So the, sometimes we do a a three quarter chip,

  771. which is a three quarter inch piece of rock

  772. and then a three eights rock.

  773. And then the three eights kind

  774. of fits into all the little holes,

  775. but on, you only do that if you need a little bit,

  776. if you're going for a little extra wear surface.

  777. But on like seventh

  778. and 16th the, the three eighths will be fine.

  779. So they'll, they'll go through, they'll do the three eighths

  780. and then when they're able, they'll come back

  781. and do what they call a fog coat,

  782. which is just spraying the black oil down.

  783. Again, that extends the life a little bit,

  784. but it also helps the, the striping show up.

  785. So when they first do it, it'll just look real gray

  786. and then that second coat makes all the striping shows up

  787. and then it holds all those rocks in a lot better.

  788. Sometimes when they do the chip seal you will see like some,

  789. they call it chip loss, especially in the first couple days

  790. where some of the rocks come up.

  791. The reason, so,

  792. and that's why we're doing these on high traffic roads.

  793. So chip seal, the best thing to do

  794. for chip seal is to drive on it.

  795. So like a road like airport road, it'll be done

  796. with its chip loss pretty quick.

  797. Whereas like residential streets sometimes aren't the best

  798. for the, the chip seal because you'll put it down

  799. and it can even take years

  800. before all those rocks quit coming up

  801. and they wind up in curb and gutter.

  802. So on the, on the residential streets, we use

  803. what's called HA five, which is, it's kind

  804. of like a seal coat, but it has a better binder so it lasts.

  805. We've got roads that we put it on four

  806. or five years ago and they look identical to the day

  807. that they put the stuff down.

  808. So it's, it's a better candidate for the low traffic roads.

  809. It basically does the same thing as chip,

  810. it costs a little bit more,

  811. but you don't wind up with all the rocks

  812. and stuff in your curb and gutter

  813. and having to deal with that.

  814. We are doing the joints

  815. and the, the surface of the bridge coming into town.

  816. So that's scheduled to start in March.

  817. That goes to council tomorrow for award.

  818. So that was part of the devolution

  819. that I talked about earlier

  820. where CDOT gave us that right of way.

  821. The actual bridge itself, the structure is still C dots,

  822. but the surface is ours, so we're gonna be doing

  823. the, the surface of it.

  824. One of the things that needs replaced is the joints,

  825. which is the structure, but we're working

  826. with CDOT on reimbursement.

  827. So we'll basically be able to do the joints

  828. and then the surface so everything will be taken care of

  829. and then anything that was their scope,

  830. they reimburse us for.

  831. I think one of the things to note with the,

  832. the bridge joints themselves is there's like the

  833. existing ones have a metal joint that has these metal studs

  834. that go into the concrete and they have to go

  835. and chip all the concrete to get those out.

  836. But just below that is the actual structure of the bridge.

  837. So they can't, if they go too deep, then they're actually

  838. could be getting into the structure.

  839. So it winds up being more tedious than a normal.

  840. Normally if you're breaking concrete you just get

  841. to go keep breaking.

  842. But the, the actual demo of the bridge joints will

  843. usually go slower than you'd think.

  844. So it can take as much as three days

  845. per per lane just for the demo.

  846. Just 'cause it's such tedious work to make sure

  847. that they're, they're getting it out but not going too deep

  848. and not causing any damage.

  849. So there'll probably be days where you drive by

  850. and wonder what they did all day.

  851. 'cause in the morning they were here

  852. and the next he would come back

  853. and they're still just right there,

  854. but it is pretty tedious work getting all that chipped.

  855. Once they get that and then get 'em poured, everything will,

  856. the milling and the asphalt will go pretty quick.

  857. So that's the, the bulk of the time is all that demo.

  858. And then once we get through that it's just mill it all

  859. and put new asphalt down

  860. Birch Avenue.

  861. So that's this year as well.

  862. It's another, it's a water project

  863. but Birch Avenue is also falling apart.

  864. So it's a, it's a good spot to be doing, doing work

  865. and replacing roadway.

  866. It's replacing a water line

  867. that goes from our new water plant,

  868. which the new water plant is here

  869. and then all the way to the Deerfield tanks,

  870. which are the big tanks you can see above the park.

  871. So this year we plan on replacing half of it

  872. and the existing line is an old ductile line

  873. that has shown enough corrosion that we definitely need

  874. to be replacing it

  875. and we're replacing the new one that the existing one kind

  876. of runs through Highlands East and it's not very accessible.

  877. It was all put in easements

  878. but now there's tough sheds right up to 'em and fences

  879. and houses and because it, it was put in well

  880. circa fifties and sixties.

  881. So a lot's changed up there since then.

  882. So the new water line will go in right of way.

  883. So not only is it replaced new,

  884. but it's also gonna be in a protected corridor

  885. where if we do need to do maintenance it winds up

  886. accessible for forever.

  887. Is that what all the pot polling was about?

  888. Yep, yep, yep.

  889. So the potholing, so as

  890. of 20 17 18,

  891. there's actually a senate bill that requires any,

  892. so any pipeline project of a certain length

  893. or any government project to do

  894. what they call a subsurface utility engineering survey.

  895. So we're required to, before we put the water line in to go

  896. and pothole every crossing, which actually when you go

  897. to put it in, relieves a lot of unde.

  898. Basically the, the intent is that when you go to build it,

  899. everything that you're crossing,

  900. you know you're gonna miss instead of digging

  901. and then the contractor finds it

  902. and now you're trying to raise the water line

  903. or lower the water line or do something to miss it.

  904. All of that's vetted in the beginning.

  905. So that's what all that pothole was. And just

  906. To comment on early potholes in the winter was

  907. they got a holes that deep they never filled back up.

  908. Okay.

    Dogwood and

  909. Birch.

  910. Dogwood and birch, okay, we'll make sure they get that.

  911. So you guys are gonna be working up there at the same time

  912. they're gonna put in, there was flagging put in for,

  913. what am I thinking?

  914. High speed internet or whatever.

  915. There's flagging along the roads

  916. and I think that's what they said they were putting in

  917. a optical fiber. Fiber. Fiber.

  918. Fiber optic fiber. Oh, fiber optics.

  919. Yes, yes.

    Is that on birch?

  920. The rug birch and then it goes up, goes up seventh.

  921. Yeah. Do you think that, did you guys do flagging up there?

  922. Did you put in flagging

  923. Any of the red pin, flex and yellow?

  924. Any of the red and yellow

  925. would've been part of that pothole.

  926. So okay, so that's, so basically what you do when you do

  927. that is you call in for locates and they come in

  928. and they locate all of the, the gas and the water

  929. and the sewer and the fiber optic, anything

  930. that's in the road, they locate it to the best

  931. that they can get with the locators.

  932. And then you look at where your water line's gonna go.

  933. And then anywhere that your water line crosses one

  934. of those you actually have to dig up

  935. and find and then survey.

  936. So they, if they're crossing a gas line, they dig it at

  937. that spot and then survey it

  938. and then that way when they do the plans for the water line,

  939. they know if they're above or below

  940. or sometimes you have to relocate things,

  941. which takes time. So, okay.

  942. I think I would be,

    Could be that,

  943. but it doesn't mean sometimes the utility companies

  944. have different schedules than we know of.

  945. So yeah.

  946. And then this, so this will be a two year, so the,

  947. this year the goal is to get tomorrow draw or ninth street

  948. and then it'll, the project will end.

  949. So the new water treatment plant treatment plant.

  950. And you guys are tying it into the water tanks? Yep.

  951. How is it tied in now? It's not at all

  952. Now it's tied in through an old ductile line

  953. that basically goes straight up through Highlands East.

  954. So it has a line that ties them in.

  955. Now it's a 16 inch that's

  956. pretty corroded.

  957. Is that one that you can run through,

  958. expand and

  959. Do the liner?

  960. No. So the risk with that is you have to shut to do it,

  961. you have to shut the water down, which

  962. because, so that's the line that feeds every drop of water

  963. and rifle goes through that.

  964. So it leaves the plant and goes through that.

  965. So we can only shut that line down for

  966. like in the summer when we're using water more like 24

  967. to 36 hours before we're all out,

  968. which unfortunately is the same time that construction

  969. season usually is too.

  970. But then the other risk is once in a while when you do those

  971. liners they can, like we've had 'em tear, so you'll go in

  972. through and pull it

  973. and if there's something in the pipe it can tear it

  974. and then now you have this tor pipe

  975. and you gotta pull it back out or they can get stuck.

  976. So there, there's a lot of risk to doing it with the liner

  977. that's for this line's not, we can't really risk

  978. running outta water

  979. and it also reduces the diameter.

  980. So the existing one's a 16 inch

  981. and the new one will have a 24 inch diameter,

  982. which will be sized to serve.

  983. If we do have growth, we'll it'll be big enough.

  984. Kinda on the same vein, so that's street project,

  985. marrow drive, so ninth Street.

  986. So it's currently, so we have it designed

  987. and we do plan on work shopping

  988. with council tomorrow on the full.

  989. So we have 1.5 million in the budget.

  990. It's kind of a tough road because it's fallen apart,

  991. but its use is, it doesn't get, it's

  992. debatable on if the use it gets is

  993. $1.5 million worth of use.

  994. So a lot of the problems it has is it has a lot of drainage

  995. that comes from the uphill side of it.

  996. And then on the downhill side you have the steep bank

  997. into the draw.

  998. So the, the plans that we have basically puts a valley pan

  999. and an under drain to get rid of the water

  1000. on the uphill side.

  1001. And then it actually has a small concrete wall

  1002. that holds the lower side.

  1003. So it makes it a pretty expensive road.

  1004. We usually are able to do, one of the reasons we're able

  1005. to do a lot of projects with fewer staff is

  1006. because we try not to do rework.

  1007. So when we go to do a road, we try to do the water

  1008. and the sewer and anything we could need.

  1009. So it's the next generation that's there

  1010. and we don't want to be back.

  1011. So one of the arguments to replacing the whole thing is

  1012. that we, we fix it and we're done

  1013. and next year we're fixing some other road

  1014. and we're not just deferring maintenance

  1015. and it turns into maybe less of a,

  1016. a financial burden, but we are fairly lean staff

  1017. so it becomes more of a time burden which isn't,

  1018. isn't negligible either.

  1019. So there'll be some level

  1020. of improvements happening this year, tomorrow drive

  1021. basically just the, the ultimate goal.

  1022. It does take a lot of traffic off of 16th

  1023. and it also lets us do work.

  1024. Like we try to make sure that we're able

  1025. to do work on streets and not have

  1026. and make sure we have some other way around.

  1027. So if we do have work that we need to do on 16th,

  1028. we can detour 'em on marrow or vice versa.

  1029. So it's important for traffic flow, very important

  1030. as we grow that we have that extra tie in there,

  1031. but just making sure that we're using our dollars the best

  1032. for, for those improvements.

  1033. But we should expect some work on there this year when we go

  1034. to do it, probably for a large portion of the work,

  1035. it'll be closed, it'll probably just be close to through.

  1036. So some of those houses that use their

  1037. back access for equipment and cars

  1038. and access for almost the entirety of the project,

  1039. we'll be able to keep access for them.

  1040. But for through traffic it'll be closed.

  1041. So the, this one is actually our, you,

  1042. this is still our street map

  1043. and you can see it's red, it's one of our worst roads,

  1044. but it's actually our highest priority

  1045. waterline project as well.

  1046. So this is Ute and fifth.

  1047. So it's basically makes up the corner of the care center.

  1048. So this project will be this year

  1049. it replaces two manholes

  1050. and a stretch of sewer line

  1051. and then replaces all the water.

  1052. And one of the big things it does

  1053. with the water replacement is, so

  1054. rifles water is on three different pressure zones.

  1055. So we have the, basically what is the,

  1056. the northeast zone.

  1057. So we have the, the tank up at the, the northeast tank

  1058. that sits, you, you may may have seen it, maybe not,

  1059. but it's up kind of the top of Grand Mesa

  1060. and that feeds basically this hilltop.

  1061. And then we have the city zone

  1062. that feeds basically everything else.

  1063. And then there's an intermediate zone,

  1064. which takes up the care center

  1065. and just kind of that surrounding area.

  1066. It's fairly small, but it only has,

  1067. right now it only has two feeds

  1068. and both of 'em are aging lines.

  1069. So by replacing this line, the valve that keeps

  1070. that zone at its pressure will also be able to bypass.

  1071. So it adds one more redundant line to the intermediate zone,

  1072. which is also the zone

  1073. that houses the VA in the care center, which are more,

  1074. are probably the VA care center

  1075. and the hospital are the most critical buildings

  1076. to keep in service.

  1077. So that water project

  1078. greatly improves the reliability of the water in that area.

  1079. Water sewer. And then it does extend sidewalk on the,

  1080. it'd be the north side of fifth.

  1081. So currently it comes up and then stops at the church

  1082. and then it Aspen starts again.

  1083. So it, it closes that gap.

  1084. There's a couple utilities that are getting moved

  1085. to the back curb so that we can do that.

  1086. But that project is, is a big water and sewer project

  1087. and then like a lot of 'em winds up replacing the street

  1088. and then adding the sidewalk as well.

  1089. And, and that one's another one that's got funding from

  1090. Garfield County Federal Mineral Lease District as well

  1091. as the Department of Local Affairs.

  1092. Both of those are energy impact money.

  1093. So energy impact money is, is a big part

  1094. of what we do.

  1095. Something that's kind of underway now

  1096. is the Park Avenue extension.

  1097. So this is Centennial Parkway

  1098. or Highway six, this is third Street

  1099. and then Park Avenue.

  1100. So at,

  1101. what we are doing is extending Park Avenue all the way down

  1102. to Highway six or Centennial Parkway. So

  1103. That go through those new apartments.

  1104. It goes just, it goes in between the theater

  1105. and the new apartments.

  1106. So that'll actually be the access for the apartments.

  1107. And this spring,

  1108. so starting in March, we'll extend Park Avenue to

  1109. where there, there needs to be a bridge

  1110. and then this over the winter we'll build the bridge

  1111. and then by late summer of 2026, we'll have

  1112. that completed.

  1113. Caught it cut your cough right there.

  1114. That's another project that got funded

  1115. from Department of Local Affairs.

  1116. So they're paying to replace the waterline

  1117. basically all the way around the apartments as well

  1118. as Park Avenue and the bridge.

  1119. So that bridge would basically never happen

  1120. without grant funding.

  1121. So it's, it's super, super big deal

  1122. that we're able to get that.

  1123. And then just across the street we have a new park

  1124. and ride going in.

  1125. So that's gonna extend the, so Park Avenue

  1126. and West Avenue will extend to the other side of Highway six

  1127. and then end at a park and ride.

  1128. We're gonna take the, the

  1129. existing parking right at the corner, basically it's going

  1130. to the back of the lot, which is privately owned

  1131. and then the person that owns

  1132. that is then gonna get a corner lot.

  1133. So it's a swap,

  1134. but basically it's benefits the city

  1135. because the more prime real estate winds up with a developer

  1136. that can do something with it.

  1137. And then we get to put in, put a parking lot adjacent to

  1138. railroad and further off the road in

  1139. maybe the less desirable.

  1140. So it puts the development

  1141. where development should do best.

  1142. So capacity will be

  1143. More?

  1144. Yep. Yeah, so there's,

  1145. there will always be at least 120 spots.

  1146. I think the plans right now call for a hundred

  1147. and I wanna say 130 spots.

  1148. So there'll be 130 parking spots for,

  1149. and there'll be for, for ride share as well as the bus.

  1150. But we do, we do see a lot of,

  1151. of ride sharing going on there.

  1152. Okay, so this is the last one.

  1153. This map is actually our sewer map.

  1154. You can see there's a lot more red on the sewer map.

  1155. So we have quite a bit more work,

  1156. quite a bit more catching up to do on some

  1157. of these sewer projects Right now.

  1158. The, the sewer fund

  1159. is hit pretty hard with the new plant that we built in

  1160. 2014.

  1161. So it was, it's a beautiful plant, it works great,

  1162. but that took quite a bit of financial burden.

  1163. So we're in the process of kinda catching sewer back up.

  1164. You can see basically it's kind of the age of development

  1165. downtown is where a lot of the oldest sewer

  1166. is and the highest priority replacements are.

  1167. This little stretch here on railroad

  1168. is actually the piece we line.

  1169. So this map's not, I need to update that,

  1170. but basically we've taken that piece of red

  1171. and turned it into a green.

  1172. But then this is ninth Street

  1173. and then White River, when we replaced,

  1174. we lined this and replaced the manhole

  1175. and then ran new line to the, to the edge of the project

  1176. and we tied into the old line

  1177. and where we did the pipe was smashed to about two inches.

  1178. So it's a, it's called Orangeburg Pipe,

  1179. which is kind of like a, it's basically,

  1180. well it's almost like paper mache.

  1181. So it's like they actually use pitch, it's like a

  1182. basically paper mache with oil instead of water

  1183. and over time it just winds up squishing.

  1184. So that one's squished to, like I said, about two inches

  1185. and it drains basically the,

  1186. the housing commercial here and then on White River.

  1187. So this year we will be replacing that.

  1188. We'll be running the sewer up ninth

  1189. Street and then White River.

  1190. And when we're on White River, we'll be able to, basically

  1191. during the mainline installation we can keep the,

  1192. the northbound open,

  1193. but then when the services go across,

  1194. there's gonna be closures on White River through those,

  1195. those portions of the project.

  1196. So out of the, the traffic impacting projects,

  1197. this one won't be basic, it won't be a super long duration,

  1198. but anytime you're messing with White River,

  1199. it'll probably have some of the higher traffic

  1200. impacts compared to some of the others.

  1201. But as you can see here, super critical project

  1202. and basically because, so a lot of pipes we're able to

  1203. run jetters up through, so we've got cleaning equipment,

  1204. so even some of the, the older lines that may

  1205. back up we're able to clean

  1206. and keep operating this line is actually collapsed

  1207. to the point where the only way if it were to back up

  1208. to fix it is to replace it.

  1209. So basically it's, it's kind of a,

  1210. a mission critical one to get replaced before,

  1211. before it plugs up.

  1212. And I think that's

  1213. All Move down.

  1214. Yeah. So yeah, I think

  1215. that is it, unless you guys have questions

  1216. or wanna go back over anything that I talked about.

  1217. So

    On the Park Avenue one, so that bridge

  1218. that's already there, are you replacing that?

  1219. I'm not.

    So the, the bridge

  1220. that's already there is on third Street.

  1221. Yeah. So what we're gonna be,

  1222. we had a better image.

  1223. Yeah. 'cause it was just kind

  1224. of confusing since Park Avenue doesn't line up

  1225. behind the movie theater.

  1226. So this is the newly theater

    Area, sorry.

  1227. And then this is that third street bridge,

  1228. but the Park Avenue will actually extend here.

  1229. So behind, it'll be actually to the west.

  1230. So it'll be entirely new road that extends.

  1231. Awesome. Okay.

    We're basically

  1232. right beside John's wood.

  1233. Yep, exactly.

    Okay.

  1234. And that's, so phase one is this year

  1235. and that gets the road up to

  1236. where we're gonna start the bridge project

  1237. and also gets access to the apartments

  1238. and that's anticipated to finish midsummer.

  1239. And then in late fall

  1240. or early winter we'll start the bridge

  1241. and then do the bridge over the winter

  1242. and then start the roadway.

  1243. So that 2026 will be when we

  1244. finish the whole extension. What

  1245. Thinking about thinking park end all the way through.

  1246. So it's, there's a few different, so a big part

  1247. of it is just traffic.

  1248. So it sets us up to where we have railroad,

  1249. which is our arterial right up the middle.

  1250. And then we have kind of our two collectors, white River

  1251. and Park Avenue on the sides.

  1252. So that ideally if we, I mean even the traffic

  1253. that we have now, it just kind of disperses it.

  1254. That makes sense. And then it also, so from just a downtown

  1255. and development, it sort of bookends downtown.

  1256. So that'll be sort of the new, the new entrance to downtown

  1257. and just kind of puts new infrastructure

  1258. and connects all these apartments to, it gives them

  1259. access to our downtown and

  1260. Good access to the program.

  1261. Exactly. Yep.

  1262. A question that we might not even be able to answer,

  1263. but the old bridge over the Colorado River.

  1264. Yes. Yeah.

    What are we gonna ever do?

  1265. There's lots of thoughts

  1266. and Kim probably has some, so it's actually owned

  1267. by the county and

  1268. it has, it has a lot more the,

  1269. it's Achilles heel is basically the railroad tracks

  1270. that are in front of it.

  1271. So we can't get an at grade crossing

  1272. to access it from this side.

  1273. So it kind of, it makes it hard to I know.

  1274. Utilize, yeah. Even

  1275. For pedestrian

    Traffic.

  1276. Yeah. Yep. So, and Kim, you can, I'm Kim Berger. Yep.

  1277. And we all think about that bridge

  1278. because it's so iconic to Rifle

  1279. and it's got a lot of benefit if we could figure out a way

  1280. to get over the railroad tracks

  1281. so we could make it a pedestrian crossing.

  1282. There's also some liabilities. We don't own it.

  1283. It is owned by the county.

  1284. It's on the National Historic Registry.

  1285. So there's

    Restrictions, so there's

  1286. so some restrictions there.

  1287. We've looked at grants to do a structural analysis

  1288. of the bridge until we do that

  1289. and get a grant to pay for that,

  1290. then we really can't even think about

  1291. anything to do with it. Can you switch

  1292. That picture to that bridge and

  1293. Yeah. Just because

  1294. This has been decades we're going on. Yeah.

  1295. Yeah. So, and, and we all think about it.

  1296. So one of the, the, the main challenge with it

  1297. is the railroad where the railroad, so from the north end

  1298. we won't be able to get access over the railroad.

  1299. Yeah. So there is one plan

  1300. or thought it's not really even a plan is a way to

  1301. maybe trail from the south

  1302. under where, or I'm sorry from the north

  1303. but the west side from where

  1304. Rifle Creek goes under the railroad,

  1305. there's potentially enough space there

  1306. to do a walking trail there

  1307. and then access it up to river that way.

  1308. There's a lot that would have to happen to do that

  1309. 'cause it crosses a lot of private land.

  1310. Well isn't that included in this new parking ride? Swap

  1311. That So it, the land doesn't,

  1312. the swap doesn't go that far down.

  1313. Oh, okay. Okay. Yep.

  1314. But that we are, we are looking at different

  1315. ways to access that.

  1316. But until we are able to get a grant to pay

  1317. for a structural analysis,

  1318. 'cause there's, it's right now the, the deck

  1319. of it is not safe to walk on.

  1320. So we kind of want to know what we would get into

  1321. before we took ownership from the county of it.

  1322. Well good luck with it. So,

  1323. but it is something that we are all thinking about

  1324. how do we capitalize on that?

  1325. Well I'm glad it's still talked about.

  1326. It is very talked about. Thank you

  1327. Mike.

  1328. And so the only other thing I wanted to touch on that Craig

  1329. sort of mentioned is just from the budget perspective, kind

  1330. of where we are with our streets.

  1331. So we, we get our money from a sales tax

  1332. for Street specifically it's three quarters of a cent

  1333. percent better than me.

  1334. And so that money is specifically allocated two streets.

  1335. The other funding source

  1336. that we have is every time anyone builds a

  1337. residential unit in the city

  1338. or a commercial unit

  1339. to a lesser extent they pay an impact fee to the city.

  1340. And it's meant to be growth paying for added

  1341. capacity onto our street network.

  1342. So that's kind of where we exist. Then the city.

  1343. 'cause we get, I, I like talking to you guys

  1344. because you're the ones

  1345. who are interested in getting yourselves educated on this.

  1346. 'cause we get a lot of questions of well the city,

  1347. you know you have such great parks, you know,

  1348. you do such good job with those

  1349. and that's a separate funding source.

  1350. So they actually, our park system gets more funding

  1351. based on city of rifle voters what they passed

  1352. than Craig gets for all the maintenance

  1353. of the street network in town.

  1354. And so that's where we're sort of at a point

  1355. that Craig mentioned, we're getting away from sort

  1356. of the cooler projects which we can get

  1357. more grant funding for.

  1358. So downtown third Street, right?

  1359. Everyone in needs to fund that project

  1360. 'cause it's cool pedestrian stuff.

  1361. We get to do fancy concrete

  1362. work, it's all that sort of stuff.

  1363. Then as we are moving away to tomorrow those kind

  1364. of projects, the grant funding is less.

  1365. So that's why the city took

  1366. a run at a sales tax increase for streets two years ago now.

  1367. And so just trying to figure out,

  1368. Craig does his calculations and we try

  1369. and hit that number exactly on

  1370. what we need total for maintenance.

  1371. 'cause right now we're operating in a deficit

  1372. with streets. Are

  1373. You gonna try that, that voting thing again

  1374. at some point? I mean

  1375. To Yeah.

  1376. You know we don't, we, I don't think council knows it lost

  1377. pretty resoundingly 60 40 so it wasn't,

  1378. it wasn't very close an option that we can explore.

  1379. So we also, another tax pot that we get is

  1380. to our general fund and that's 2%

  1381. goes into the general fund, which is sort of the, the fund

  1382. that we can use for all things.

  1383. But because it has a lot of needs associated with it.

  1384. So like the entire police department is

  1385. funded out of the general fund.

  1386. Lots of our public works and snow plows

  1387. and that sort of thing comes outta general fund.

  1388. So we're working on how can we sort

  1389. of subsidize the street fund in the meantime

  1390. 'cause Craig's doing such great work on all these projects,

  1391. we're really getting our

  1392. streets up to where they need to be.

  1393. But it's sort of just figuring out that funding piece.

  1394. So yeah, if you guys got advice on when

  1395. to take another run outta the street tax, I dunno we take it

  1396. something just timing wise too, like our sort

  1397. of like the drop dead is so

  1398. probably like 20, 30 ish.

  1399. And a lot of that is if you, especially people

  1400. that have been here for a long time, if you think back

  1401. to like pre 2000, like late nineties

  1402. when we didn't have Pasture

  1403. North Pasture, we didn't have most of Deerfield

  1404. North rifle, Palomino Park was just kind

  1405. of getting plowed in.

  1406. And then from there to 2008,

  1407. like almost 33% of rifle built,

  1408. which means that all that a third

  1409. of rifle streets will basically come to needing replacement

  1410. all about the same time.

  1411. So that's gonna hit, that was all

  1412. in the early two thousands.

  1413. So in the mid 20, like 2030 to 2040

  1414. is when a huge chunk of all of our stuff

  1415. that seems relatively new now

  1416. will all start failing kind of all at the same time.

  1417. So some of that's just trying to hedge, we, we've kind

  1418. of made it through the, the eighties boom on some of

  1419. that infrastructure, but we'll, we'll kind of have

  1420. that same thing happen again to us in, well not,

  1421. not that far, 10 years down the road.

  1422. So making sure we're in a spot that we can see that coming

  1423. and then handle it when it does come.

  1424. Cool. Really good projects.

  1425. And utilizing your funding,

  1426. Do you get any funds?

  1427. We do, I think

  1428. so every year.

  1429. So straight tax usually winds up being about 1.4 million

  1430. and I wanna say HUTF is like on the 60

  1431. to a hundred thousand.

  1432. So it's, we get it

  1433. but it's not, not a whole lot on what it,

  1434. on the grand grand scheme this year we've actually,

  1435. we've almost optimized our grant usage.

  1436. So usually a grant you, you apply to get a grant

  1437. and the most they usually fund is like 80%.

  1438. So they'll fund 80 20

  1439. or 60 40 this year.

  1440. We've actually, we've I think between,

  1441. basically between 60

  1442. and 80% of our funding this year is grant funding.

  1443. So we've almost used all of our funds as a match.

  1444. So we, this year especially,

  1445. we basically couldn't squeeze another penny out

  1446. of the pennies that we, we have to work with.

  1447. And then some of those grants, they're, they're kind

  1448. of cyclical.

  1449. So most of the ones we get are from federal mineral lease.

  1450. So they're kind of oil and gas related

  1451. and they seem to sometimes even when it's,

  1452. I don't know if they lag the booms,

  1453. but they, from year to year it seems like we get

  1454. a pretty wide, wide variety of funding.

  1455. So some of it's political

  1456. but then some of it might just be how much they're producing

  1457. and then things that are just out of everybody's control.

  1458. So the, the tax also gives us,

  1459. puts us a little bit more control of our own destiny.

  1460. Thank you for doing

    Thank you.

  1461. No thank you guys for, for coming.

  1462. Thank you guys very much.

  1463. The next one we have will be sometime in the beginning

  1464. of summer, we're still sort of working out.

  1465. We're gonna do a quarterly one of these.

  1466. So appreciate you guys have been to all these we'll give

  1467. but certificate but we're still working through

  1468. what we wanna see at the next one.

  1469. So if anyone has any ideas,

  1470. Angelica will send out a little survey you guys

  1471. and yeah, appreciate you taking the time

  1472. and really appreciate Craig.

  1473. He's, yes, he can tell a lot of his stories.

  1474. Start with, well about five

  1475. or six years ago, we were not in the best place in that.

  1476. He wouldn't say that 'cause he started

  1477. about five or six years ago.

  1478. We're now in the, in the place where we are.

  1479. So we're lucky to have good staff.

  1480. Like, so appreciate you guys coming back. Back. Cool.

  1481. Thank you. Thank you.

City of Rifle events & activities (113 Videos)
Updated 5 days ago

Events & Activities hosted by, regarding, or in connection to the City of Rifle, Government. Find this playlist and More @ www.RifleCO.org/CityVideos

  1. 1
    02:04:55
    Rifle City Council • Dec 17, 2025
  2. 2
    00:10:27
    Rifle Hometown Holidays: Assorted Events Around Town • Dec 6, 2025
  3. 3
    00:17:32
    Rifle Hometown Holidays: Fireworks Show • Dec 6, 2025
  4. 4
    00:22:09
    Rifle Hometown Holidays: Parade of Lights • Dec 6, 2025
  5. 5
    01:44:57
    Rifle Planning & Zoning Commission • Dec 9, 2025
  6. 6
    00:40:28
    Rifle Parks & Recreation Advisory Board • Dec 8, 2025
  7. 7
    02:01:10
    Rifle City Council • Dec 3, 2025
  8. 8
    01:05:54
    Rifle City Council • Nov 20, 2025
  9. 9
    00:25:06
    City of Rifle • Community Development • Plan Jam 2.0 community meeting • Nov 18, 2025
  10. 10
    00:41:53
    Rifle Parks & Rec • Community Meeting • Rifle Activity Center Feasibility Study • Nov 17, 2025
  11. 11
    00:18:48
    Rifle Mountain Park • A World Renowned Rock Climbing Area
  12. 12
    02:39:13
    Rifle City Council • Nov 5, 2025
  13. 13
    00:11:39
    Rifle Downtown Halloween Parade & Trunk or Treat - Oct 31, 2025
  14. 14
    00:16:12
    Rifle Planning & Zoning Commission • Oct 28, 2025
  15. 15
    01:26:18
    Rifle City Council • Oct 16, 2025
  16. 16
    00:53:04
    Rifle Parks & Recreation Advisory Board • Oct 13, 2025
  17. 17
    00:18:25
    Colorado River Fire Rescue • Open House • Sep 20, 2025
  18. 18
    01:17:12
    Rifle City Council • Oct 1, 2025
  19. 19
    00:43:58
    Rifle Planning & Zoning Commission • Sep 30, 2025
  20. 20
    00:49:44
    Rifle Parks & Rec • Community Meeting • Rifle Activity Center Feasibility Study • Sep 25, 2025
  21. 21
    00:54:18
    Rifle City Council • Sep 17, 2025
  22. 22
    00:35:08
    Rifle Parks & Recreation Advisory Board • Sep 8, 2025
  23. 23
    00:52:01
    Rifle City Council • Sep 3, 2025
  24. 24
    00:09:22
    Birch Park GroundBreaking Ceremony • Aug 27, 2025
  25. 25
    00:45:20
    Rifle Planning & Zoning Commission • Aug 26, 2025
  26. 26
    01:23:24
    Rifle City Council • Aug 20, 2025
  27. 27
    00:53:58
    Rifle Parks & Recreation Advisory Board • Aug 11, 2025
  28. 28
    01:11:39
    Rifle City Council • Aug 6, 2025
  29. 29
    00:58:55
    Rifle Planning & Zoning Commission • Jul 29, 2025
  30. 30
    00:03:14
    What is GRIT • An Overview with Kim Burner
  31. 31
    00:47:03
    Rifle City Council • July 16, 2025
  32. 32
    00:46:18
    Noodle Soup 3rd of July concert • Jul 3, 2024
  33. 33
    01:12:37
    Symphony in the Valley: "Independence Day" concert • Jul 3, 2025
  34. 34
    00:49:30
    Feeding Giants 3rd of July concert • Jul 3, 2024
  35. 35
    00:11:07
    3rd of July Activities @ Metro Park • Jul 3, 2025
  36. 36
    01:19:47
    Kenny Stanley Memorial BMX, Scooter & Skate Comp • Jun 21
  37. 37
    01:24:32
    Rifle City Council • Jul 2, 2025
  38. 38
    00:31:05
    Rifle Planning & Zoning Commission • Jun 24, 2025
  39. 39
    00:45:08
    Rifle City Council • June 18, 2025
  40. 40
    01:07:41
    Rifle City Council • June 4, 2025
  41. 41
    00:34:32
    Rifle Planning & Zoning Commission • May 27, 2025
  42. 42
    01:16:11
    Rifle City Council • May 21, 2025
  43. 43
    01:10:51
    Rifle City Council • May 7, 2025
  44. 44
    00:21:14
    Rifle Planning & Zoning Commission • Apr 29, 2025
  45. 45
    00:52:27
    Rifle City Council - Apr 16, 2025
  46. 46
    01:07:41
    Rifle City Council - Apr 2, 2025
  47. 47
    01:21:01
    Rifle City Council - Mar 19, 2025
  48. 48
    01:11:00
    Rifle City Council - Mar 5, 2025
  49. 49
    00:23:11
    Rifle Planning & Zoning Commission - Feb 25, 2025
  50. 50
    00:12:09
    City of Rifle: "State of the Community" video - 2025
  51. 51
    01:10:40
    Rifle City Council - Feb 19, 2025
  52. 52
    01:23:03
    City of Rifle: Streets Projects Open House - Feb 18, 2025
  53. 53
    00:50:39
    Rifle City Council - Feb 5, 2025
  54. 54
    00:23:09
    Rifle Planning & Zoning Commission - Jan 28, 2025
  55. 55
    01:17:12
    Rifle City Council - Jan 15, 2025
  56. 56
    01:05:55
    Rifle City Council - Dec 18, 2024
  57. 57
    02:21:56
    Rifle Planning & Zoning Commission - Dec 17, 2024
  58. 58
    00:38:19
    Rifle Hometown Holidays: Fireworks and Parade of Lights - Dec 7, 2024
  59. 59
    00:33:07
    Rifle City Council - Dec 4, 2024
  60. 60
    00:29:07
    Rifle City Council - Nov 20, 2024
  61. 61
    00:10:45
    Rifle Planning & Zoning Commision - Oct 29, 2024
  62. 62
    00:20:05
    Rifle Downtown Halloween Parade & Trunk or Treat - Oct 25, 2024
  63. 63
    01:45:33
    Rifle City Council - Oct 16, 2024
  64. 64
    00:55:28
    Rifle City Council - Oct 2, 2024
  65. 65
    00:25:39
    Rifle Apartments Groundbreaking (@ 115, 123, & 131 Park Ave) - Sep 27, 2024
  66. 66
    00:55:47
    Rifle City Council - Special Meeting - Sep 25, 2024
  67. 67
    00:29:48
    Rifle Planning & Zoning Commission - Sep 24, 2024
  68. 68
    00:22:28
    RPD Unscripted: Guiding the next Generation w/ "Detective Sergeant Ryan and Officer Burris" - Aug 27, 2024
  69. 69
    00:20:27
    RPD Unscripted: Guiding the next Generation w/ "Lieutenant Kuper and Officer Dunn" - Aug 27, 2024
  70. 70
    01:33:13
    Rifle City Council - Sep 18, 2024
  71. 71
    00:57:08
    Rifle City Council - Sep 4, 2024
  72. 72
    00:02:29
    Building Birch Park - recreation participant interviews
  73. 73
    01:09:37
    Rifle Planning & Zoning Commission - Aug 27, 2024
  74. 74
    00:57:03
    Rifle City Council - Aug 21, 2024
  75. 75
    01:18:14
    Rifle City Council - Aug 7, 2024
  76. 76
    01:18:46
    Rifle Planning & Zoning Commission - Jul 30, 2024
  77. 77
    00:09:01
    Senior Center Lunch-n-Learn: "Rifle Parks & Rec" - Jul 26, 2024
  78. 78
    01:07:33
    Rifle City Council - Jul 17, 2024
  79. 79
    00:08:08
    City of Rifle - 3rd of July Activities @ Metro Park - Jul 3, 2024
  80. 80
    00:54:50
    Bluesberry Jam concert @ Centennial Park - Jul 3, 2024
  81. 81
    01:59:13
    Symphony in the Valley: "Independence Day" concert and City of Rifle: Fireworks show - Jul 3, 2024
  82. 82
    00:30:21
    Senior Center Lunch-n-Learn: "Meet Chief Funston" - Jun 28, 2024
  83. 83
    00:41:42
    Rifle City Council - Jun 19, 2024
  84. 84
    00:57:41
    Rifle City Council - June 5, 2024
  85. 85
    00:27:07
    Rifle Planning & Zoning Commission - May 28, 2024
  86. 86
    00:20:57
    Senior Center Lunch-n-Learn: "City Projects with the City Manager" - May 24, 204
  87. 87
    00:47:27
    Rifle City Council - May 15, 2024
  88. 88
    01:16:14
    Rifle City Council - May 1, 2024
  89. 89
    01:37:19
    Rifle Planning & Zoning Commission - Apr 30, 2024
  90. 90
    01:40:39
    Rifle City Council - Apr 17, 2024
  91. 91
    00:43:08
    Rifle City Council - Apr 3, 2024
  92. 92
    00:38:16
    Rifle Planning & Zoning Commission - Mar 26, 2024
  93. 93
    00:58:51
    Rifle City Council - Mar 20, 2024
  94. 94
    00:18:13
    Senior Center - Lunch-n-Learn: "City Public Works Department" - Mar 14, 2024
  95. 95
    00:10:30
    City of Rifle: "State of the Community" video for 2023-2024
  96. 96
    01:05:58
    Rifle City Council - Mar 6, 2024
  97. 97
    00:41:18
    Rifle Planning & Zoning Commission - Feb 27, 2024
  98. 98
    00:26:10
    Senior Center - Lunch-n-Learn: "Avoid Being A Scam Victim" - Feb 16, 2024
  99. 99
    01:00:35
    Rifle City Council - Feb 21, 2024
  100. 100
    01:00:38
    Rifle City Council - Feb 7, 2024
  101. 101
    02:16:54
    Rifle City Council - Jan 17, 2024
  102. 102
    00:17:56
    Rifle Hometown Holidays Parade of Lights - Dec 2, 2023
  103. 103
    00:03:09
    Rifle Police Department Employment Opportunities Video
  104. 104
    01:03:07
    Making History: Rifle Heritage Center Welcomes Police Chief Debra Funston - Mar 13, 2022
  105. 105
    00:09:10
    Spotlight: Rifle Operations & Maintenance "Snow Removal"
  106. 106
    00:04:53
    "Smile, Greet & Wave 101" - Rifle Humanity Restoration Crew
  107. 107
    00:05:02
    "Making Waves in Rifle" - Rifle Humanity Restoration Crew
  108. 108
    00:01:38
    Trees & Clearances - Rifle Police Department - Property Vegetation
  109. 109
    00:07:52
    When to Call 911 PSA
  110. 110
    00:01:46
    Snow & Ice Removal - Rifle Police Department Sidewalks Video
  111. 111
    00:01:13
    Animals Left In Vehicles - Rifle Police Department Animal Neglect Video
  112. 112
    00:01:00
    Leash Law - Rifle Police Department Animal Management Video
  113. 113
    00:01:19
    Barking Dogs - Rifle Police Department Animal Disturbances Video